This three unit triplex was in desperate need of renovations when we were approached by the owner. At the initial meeting and discussions of the extensiveness of this remodel, the homeowner informed us of a tight deadline – six weeks away! Taking on the project meant 100+ hours each week for the entire team, but we were able to pull it off. The units were approximately 600 sf each, and were gutted down to the studs. The remodel included all new plumbing, wiring, insulation, sheetrock throughout, flooring, trim, cabinets, appliances, trim, carpet and paint. When the dust settled, the owner was completely satisfied and the crew took a few days off to rest.

  

  • Gut 1800 sf triplex
  • Re-plumb
  • Re-wire
  • Insulate and air seal
  • Repair failing floor system
  • New hardwood flooring and carpet throughout
  • Sheetrock entire building
  • Cabinets and trim
  • Fresh paint throughout
  • All complete in 5 weeks!

Before:

After: